Construction Update

Where We Are



January
  • Acquire materials, prepared site for steel superstructure

February

  • Acquire steel

March

  • Pour concrete slab
  • Begin steel superstructure

April

  • Finish steel superstructure and prepare for facility construction

May

  • Lay down rink slab for North rink
  • Finish electrical and lighting in North rink
  • Complete centre core masonry

June

  • Start North ice rink construction
  • Finish electrical and lighting in South rink
  • Begin Main Entrance construction

July

  • Start tenant improvements
  • Finish North ice rink construction and begin South ice rink construction

August

  • Finish South ice rink construction
  • Continue tenant facility improvements and construction

September

  • Continue tenant facility improvements and construction
  • Complete ice rinks

October

  • Finish tenant facility improvement and construction
  • Open ice rinks for 2009/2010 hockey season

November and December

  • Additional enhancements
  • New security and booking systems
  • Ice plant and surface upgrades

Spring 2010

  • Drought and erosion resistant landscaping
  • Grand opening


For inquiries about sports centre programming, administration, or fundraising please contact:

Spray Lake Sawmills Family Sports Centre
Phone: 403-932-1635
Fax: 403-932-1625
E-mail: info@slssportscentre.com






Spray Lake Sawmills Family Sports Centre, Cochrane, Alberta, Canada